A dilapidations surveyor prepares or responds to claims that a commercial tenant has broken the repair, decoration or reinstatement rules in their lease. When a tenancy ends, the landlord usually issues a schedule of dilapidations and a quantified demand, and the tenant relies on an experienced chartered building surveyor to challenge or negotiate the figures. This guide covers commercial property in England and Wales, where specific rules and a Ministry of Justice protocol apply.
What dilapidations means in a commercial lease
Dilapidations are breaches of lease covenants relating to the condition of a property during the tenancy or when the lease ends. When a business rents a commercial space, the contract dictates exactly how the building must be kept. If the tenant fails to meet these standards, the landlord has the right to make a dilapidations claim.
These breaches usually cover a wide range of issues. They can include failing to repair damage, allowing the decoration to deteriorate, ignoring legal compliance standards, or leaving behind alterations that should have been removed.
The lease is the starting point for everything. Because every contract is different, a solicitor should advise on what the lease clauses mean in your specific case. A surveyor cannot give legal advice on contracts or litigation.
This guide covers commercial property in England and Wales. Other parts of the UK have their own law, so you must seek local advice if your premises are in Scotland or Northern Ireland. While the formal rules apply to commercial disputes, the principles are likely to be regarded as best practice in residential disputes too.
Advice to get before you sign a lease
The best time to think about dilapidations is before you agree to the tenancy. Before signing a lease, a chartered building surveyor can advise on the implications of the clauses. Your solicitor advises on what the clauses mean, and the surveyor can explain what they could mean in practice for that building.
To protect yourself, you can instruct your surveyor to carry out a photographic schedule of condition. This involves a detailed inspection to record the premises exactly as they are on the day you take them over. This may limit your repairing liability, because it records any problems, such as a leaking roof or damaged floors, that were there before you moved in.
However, these records of condition must be attached to the lease before signing so they form part of the contract. Photographs kept separately will not form part of the lease.
Alterations and party wall rules
You must also think about any work you plan to do to the building. If you make alterations during the lease, the landlord may require you to reinstate them before you hand the keys back.
If those alterations involve work on a party wall or near a neighbour's foundations, the Party Wall etc. Act 1996 may also apply, and our guide explains when you need a party wall surveyor.
The documents you will see
The dilapidations process revolves around three main documents:
- A schedule of dilapidations prepared by the landlord or their surveyor, listing outstanding reinstatement, repair, legal compliance and decoration items.
- A quantified demand issued by the landlord after the lease ends, setting out their likely loss.
- A response and Scott schedule prepared by the tenant or their surveyor, which acts as an extended version of the schedule with the tenant's replies.
The schedule of dilapidations is the starting point. It lists every individual breach of the lease covenants, alongside suggested remedial works and sometimes costs.
The quantified demand is a separate document. It translates the physical breaches into a financial claim, setting out the landlord's likely loss, which may differ from the raw cost of works shown in the schedule.
The tenant's response is usually a formal letter accompanied by the Scott schedule. A Scott schedule adds extra columns to the landlord's original schedule so the tenant can provide their replies to every single point.
The timetable under the dilapidations protocol
Claims in England and Wales follow a timetable set out in the Dilapidations Protocol published by the Ministry of Justice. The protocol expects both parties to share information openly and act without delay.
Under the protocol, the landlord should send the schedule of dilapidations within a reasonable time. This will generally be within 56 days after the tenancy ends.
The landlord should also send the quantified demand within the same timescale. This ensures the tenant knows the full extent of the financial claim shortly after leaving the property.
The tenant should then respond within a reasonable time. This is usually within 56 days after the quantified demand is sent. Sticking to this timetable helps both sides resolve the dispute quickly and keeps legal costs down.
Why the claim can be lower than the cost of works
A common mistake is assuming the tenant must pay the exact total shown in the schedule of dilapidations. In reality, the quantified demand may be lower than the cost in the schedule.
This happens because landlords should not profit from dilapidations payments. The law does not allow the claim to exceed the amount by which the property has been devalued by the tenant's breaches at the end of the lease.
The landlord's plans for the building matter a great deal. For example, if the landlord plans to redevelop the site and tear down walls, the tenant's failure to paint those walls may cause the landlord little or no loss. The same rule applies if a new tenant wants the premises as they are. If the new occupier intends to keep the alterations you made, the landlord's loss, and so the claim, may be lower.
The reduction in the property's value caused by the breaches is known as the diminution in value. Where the claim is based on a diminution valuation, it should be prepared by a valuer rather than a building surveyor.
What a surveyor does for a tenant
Near the end of the lease, it is normal for a tenant to engage a chartered building surveyor experienced in dilapidations.
Your surveyor will visit the premises to compare the landlord's schedule against the actual condition of the building. They will read your lease terms to check if you are genuinely responsible for every item listed.
They will then prepare your formal response and the Scott schedule. They will challenge any exaggerated costs, point out where the landlord's redevelopment plans make repairs unnecessary, and suggest cheaper ways to meet your obligations.
Normally the two surveyors meet to narrow the differences. They will negotiate line by line to agree on as many points as possible and recommend a settlement to you.
What a surveyor does for a landlord
Landlords normally engage a chartered building surveyor to prepare the schedule of dilapidations. The surveyor will carry out a detailed inspection to spot every breach of the repair, decoration and reinstatement covenants.
During this process, the landlord's surveyor will ask about the landlord's intentions for the property. They need to know if you plan to demolish the building, refurbish it entirely, or let it out again immediately.
This is because the protocol says the schedule should be endorsed, confirming that full account has been taken of your intentions for the property.
Once the schedule is served, your surveyor will meet the tenant's surveyor. Their goal is to negotiate a fair financial settlement that reflects your true loss, without the delay of going to court.
Settling without going to court
The main goal of the dilapidations protocol is to help both sides settle the dispute without a judge. The protocol requires parties to consider alternative dispute resolution before court. Your options include:
- Expert determination to rule on a technical issue.
- Mediation to help both sides negotiate a compromise.
- Arbitration to provide a binding decision without a judge.
Neither side can be forced into it, but an unreasonable refusal may be taken into account by the court on costs.
Complex cases may need a diminution valuation by a chartered valuation surveyor to assess how much the property's value has been reduced. If the dispute does reach a courtroom, your surveyor may be called to give evidence. A surveyor acting as an expert witness owes their duty to the court, meaning they must give honest, objective answers rather than just arguing your case.
How to choose a dilapidations surveyor
Both tenants and landlords need a professional who understands commercial property law and construction. You should look for AssocRICS, MRICS or FRICS after a surveyor's name, which shows they are a member of the Royal Institution of Chartered Surveyors.
You should also look for the words RICS Regulated for the firm. You can confirm both the individual and the firm on the RICS Find a Surveyor service. RICS regulated firms must have a complaints handling procedure, hold professional indemnity insurance, and give consumers free access to an independent alternative dispute resolution provider. While the RPSA is another recognised body for residential surveyors with its own survey products, dilapidations is a commercial discipline, so you will usually look for an RICS qualified professional.
When you contact a surveyor, ask about their experience with your specific type of property and the local area. Ensure they are prepared to endorse the schedule or response in line with the protocol.
Always get their fee basis in writing before you instruct them, and ask about recent cases similar to yours.
Read the terms of engagement so you know what the surveyor will and will not do, and check whether a diminution valuation is included if your case may need one.
Common questions
What is a dilapidation surveyor?
A dilapidation surveyor is a chartered building surveyor who prepares or responds to claims about the physical condition of a rented commercial property. They inspect the building, interpret the repair clauses, and negotiate a settlement when a lease ends.
Does the dilapidations protocol apply to residential property?
The dilapidations protocol only applies to commercial disputes. However, RICS guidance states that it is likely to be regarded as best practice in residential disputes.
Do I have to remove alterations I made during the lease?
It depends on your lease, so ask your solicitor. If you make alterations during the lease, the landlord may require you to reinstate them, and whether the landlord or a new tenant wants to keep the changes can affect the size of any claim.
Who prepares a diminution valuation?
Where the claim is based on a diminution valuation, it should be prepared by a valuer. This is usually a chartered valuation surveyor, who assesses how much the tenant's breaches have devalued the property.
What to do next
When gathering prices, get two or three like-for-like quotes that state:
- The exact level of service being provided.
- Whether a diminution valuation is included in the price.
- The expected turnaround time for the response or schedule.
You should then follow these steps to manage the process:
- Read your lease carefully and ask a solicitor to explain your exact repairing and reinstatement obligations.
- Engage a chartered building surveyor experienced in dilapidations well before your lease ends.
- Ask the surveyor about their experience with your property type and whether they will talk the report through by phone.
- Work with your surveyor to gather any photographic schedules of condition that were attached to your lease.
- Wait for the landlord's schedule and quantified demand, then let your surveyor negotiate the Scott schedule on your behalf.
- Use the findings to get repair quotes, then decide whether to proceed with negotiations or push for alternative dispute resolution.
If you are ready to prepare for the end of your lease, you can find a surveyor near you to discuss your property and get your response underway.